This from the Upper House on the 29th March...
Lord Berkeley (Labour)
To ask Her Majesty's Government what financial contribution they have committed to the Cambridge guided busway project; what is its expected opening date; what is the estimated outturn cost; and whether they intend to contribute further funding to the project.
Lord Adonis (Secretary of State, Department for Transport; Labour)
The Department for Transport's contribution has been capped at a maximum of £92.5 million. There is no intention to contribute further to this scheme. When approved in 2006 the scheme had an expected outturn cost of £116.3 million. I understand that Cambridgeshire County Council has recently indicated that the total may now fall between £140 million and £145 million.
I also understand that the council is in regular contact with the guided busway contractors regarding establishing an opening date.
And Pilate washed his hands...
Grimsby and Back
3 years ago